Finley Photovoltaic Power Plant


1.Finley Project Overview:

finley solar farm birubi

The project is located in Finley, New South Wales, about 300 kilometres north of Melbourne and just 20 kilometres from the Victorian border. The project includes a 6.5MW photovoltaic power plant and a 10MW, 2-hour battery energy storage system (BESS) connected to the 22kV main grid.

Power generation capacity: 6.5MW photovoltaic module + 10MWh battery energy storage system (BESS)
Project location: Finley, Southern New South Wales
Grid network: TransGrid 22kV
Site area: 14 hectares (34.6 acres)
Access voltage: 22kV
Lease term: 25 years
Power generation assets:
• PV modules: 10,320 630W modules (total capacity 6.5MW)
• Inverter: 1 x Sungrow SG4950HV-MV inverter
• Proposed access capacity: 4.95MW (access capacity will be evaluated as development progresses)
• Annual power generation: 13,783 MWh/year (based on 6.5MW of PV capacity)
• Battery Energy Storage System: 4 sets of Sungrow ST2752UX batteries (2.752MWh in a single set) for a total of 10MWh

 

2.Project Address:

The Finley PV plant is located within the jurisdiction of Berrigan Shire Council, about 450 kilometers west of Sydney. The town of Finley itself has a population of about 2,500 people. The nearest major city is Albury, 140 km east of Albury, with a population of about 57,000. Albury is served by a regional airport and Qantas flies to and from Qantas daily.

 

finely solar farm birubi

The PV plant is located approximately 3.4 kilometers southeast of the town of Finley and has direct access to the state’s 22kV main transmission line.

 

finley solar farm birubi

 

The project’s proximity to towns offers significant advantages, including:

  • Close to local substations
  • Reduce grid losses
  • Improve overall financial returns

3.Development Status and Delivery Pathway

The Finley PV plant is located at 728 Plumptons Road and is directly connected to a 22kV high-voltage grid line laid parallel to the plot boundary. Key workstreams include land control, planning approvals, grid coordination, EPC preparation, procurement planning, construction execution, grid connection and commercial operation readiness.

finley solar farm birubi

Detailed development milestones, approval status and transaction documents can be made available to qualified counterparties under NDA.

  • Land lease: 25 years, Completed
  • Development approvals: Approved, March 2026
  • Grid Connection Agreement:Target May 2026
  • EPC tendering: Completed, April 2026
  • EPC work starts: June 2026
  • Completion time:Approx 6 months